An alternative for improving setup times and time between failures aiming at manufacturing lead time reduction

dc.contributor.authorMarcel Utiyama
dc.contributor.authorGODINHO FILHO, M.
dc.contributor.authorOPRIME, P. C.
dc.contributor.authorOrcidhttps://orcid.org/0000-0003-0917-1079
dc.date.accessioned2022-01-12T21:53:37Z
dc.date.available2022-01-12T21:53:37Z
dc.date.issued2021-10-05
dc.description.abstract© 2021, German Academic Society for Production Engineering (WGP).The main goal of this study is to propose an alternative approach to improve manufacturing setup time and the time between failures. This approach focuses on eliminating the outliers concerning manufacturing setup times and time between failures. With this aim, we performed simulations to compare the effect on the lead time of both improvement strategies with the traditional strategies of reducing the mean or variability. The simulation results indicate that for low variability, the best strategy is to focus on the mean setup time and time between failures and the worst-case strategy emerges as an excellent practical alternative. For environments with moderate variability, investing in eliminating the worst-case setup time and time between failures is suggested as the best option. Both options presented results like the strategies of improving the mean and variability and it is generally achieved with a lower cost and easier implementation. Therefore, the results of the present study indicate that the worst-case strategy is an important improvement option and can be adopted by companies in practice, deserving further investigation in manufacturing and operations-management studies.
dc.description.firstpage651
dc.description.issuenumber5
dc.description.lastpage665
dc.description.volume15
dc.identifier.citationUTIYAMA, M.; GODINHO FILHO, M.; OPRIME, P. C. An alternative for improving setup times and time between failures aiming at manufacturing lead time reduction. Production Engineering. v. 15, n. 5, p. 651-665, oct. 2021.
dc.identifier.doi10.1007/s11740-021-01048-0
dc.identifier.issn1863-7353
dc.identifier.urihttps://repositorio.fei.edu.br/handle/FEI/3553
dc.relation.ispartofProduction Engineering
dc.rightsAcesso Restrito
dc.subject.otherlanguageManufacturing lead time reduction
dc.subject.otherlanguageProcess improvement
dc.subject.otherlanguageSetup improvement
dc.subject.otherlanguagetime between failures improvement
dc.subject.otherlanguageWorst case strategy
dc.titleAn alternative for improving setup times and time between failures aiming at manufacturing lead time reduction
dc.typeArtigo
fei.scopus.citations5
fei.scopus.eid2-s2.0-85104270176
fei.scopus.subjectImprovement strategies
fei.scopus.subjectLeadtime
fei.scopus.subjectManufacturing lead-time
fei.scopus.subjectManufacturing setups
fei.scopus.subjectOperations management
fei.scopus.subjectSet-up time
fei.scopus.subjectTime between failures
fei.scopus.updated2024-07-01
fei.scopus.urlhttps://www.scopus.com/inward/record.uri?partnerID=HzOxMe3b&scp=85104270176&origin=inward
Arquivos
Coleções